Traffic Troubleshooter: When will IDOT's phase 2 of the Kennedy Expressway construction start?

Thursday, February 29, 2024
When will phase two of Kennedy construction start?
ABC7 Roz Varon has an update in this week's Traffic Troubleshooter.

CHICAGO (WLS) -- Our coverage of this story has moved here.



The first phase of the massive multi-year construction project on the Kennedy Expressway opened in December.





Phase two the $150 million project will focus on the express lanes.



But, when will phase two start?



Illinois Department of Transportation officials were anticipating the construction to begin mid-March, weather permitting.



"With this unusually mild weather, things are moving faster than originally planned," Illinois Department of Transportation Public Information Officer Maria Castaneda said. "There are still a lot of moving parts. We don't have the specific yet, but details will arrive very soon."



MAKING HEADLINES: City Club of Chicago hosts discussion on state of Mag Mile shopping district



Although it's not a specific answer, we are anticipating an announcement sometime in the next two weeks.



There are a total of three phases to the plan. Phase two is expected to end by fall 2024.



The plan is to complete the entire project by 2025.



READ MORE: Kennedy Expressway inbound lanes fully reopened